Many villages need affordable homes for local people, but have no land allocated for housing. Rural exception sites are designed to fill that gap.
Rural exception sites allow affordable housing on land where new homes would not normally be permitted, provided it meets an identified local need and normally stays affordable in perpetuity.
For landowners, a rural exception site can be a way to bring forward land on the edge of a village that would not otherwise get planning permission.
It can also leave a lasting benefit for the local community.
This guide explains how policy HO10 of the August 2026 National Planning Policy Framework (NPPF) works, what is required, and what landowners should expect.
What Is a Rural Exception Site?
The NPPF glossary defines rural exception sites as sites used for affordable housing in perpetuity where sites would not normally be used for housing.
Rural exception sites seek to address the needs of the local community by accommodating households who are either current residents or have an existing family or employment connection.
A proportion of market homes may be allowed on the site at the council's discretion, for example where this is essential to enable the affordable homes to be delivered without grant funding.
What Does Policy HO10 Say?
Policy HO10 says development proposals for housing on land not already allocated, and located outside settlements, should be supported where they are:
a rural exception site providing affordable housing to meet identified local needs, evidenced through a local housing needs survey or secondary data no more than five years old; or
community-led development.
Unless the development plan says otherwise, exception sites should:
adjoin or be physically well-related to a settlement
not involve built development greater than one hectare, or 5% of the size of the existing settlement, whichever is greater, unless the development plan specifically allows these limits to be exceeded
include one or more types of affordable housing. A proportion of market homes may be allowed where essential to enable the delivery of affordable units without grant funding
Rural exception sites are also one of the forms of development listed in policy S5(1)(f). Where a proposal meets HO10, it should be approved unless its benefits would be substantially outweighed by adverse effects. That is a strong presumption in favour.
The Key Requirements in Practice
Evidence of local need
The need must be identified and evidenced.
The NPPF says the evidence should come from a local housing needs survey or secondary data that is no more than five years old.
In practice, many schemes start with a parish housing needs survey, often carried out with the parish council and a rural housing enabler. Councils' housing registers can provide supporting evidence.
The number and type of homes proposed should reflect that evidence: the mix of sizes, and the balance between rented and shared ownership homes.
Location
The site should adjoin or be physically well-related to a settlement.
The NPPF's definition of a settlement includes villages but not hamlets or scattered groups of houses, unless the development plan defines them as settlements.
Sites therefore usually sit on the edge of a village, with safe pedestrian access to whatever services exist.
Size
The one hectare / 5% limit is new in the 2026 NPPF.
For most villages, one hectare will be the operative limit. It is enough for a meaningful scheme, but it rules out larger extensions presented as exception sites.
Local plans can set different limits.
Affordable in perpetuity and local connection
The affordable homes are secured through a section 106 agreement. This normally includes:
a requirement that the homes remain affordable in perpetuity
a local connection "cascade", giving priority first to people with a connection to the parish, then neighbouring parishes, then the wider district
arrangements for a registered provider or community organisation to own and manage the homes
Market homes for cross-subsidy
Where grant funding is not available, a proportion of market homes may be allowed to make the scheme viable. Councils typically expect a viability appraisal to show that the market element is the minimum needed. Local plans often set a maximum proportion. Cross-subsidy can make a scheme work without public funding, but it is the area where councils scrutinise proposals most closely.
Community-Led Development
HO10 also supports community-led development on unallocated land outside settlements.
The NPPF defines this as development taken forward by, or with, a not-for-profit organisation that exists primarily to meet the needs of its members or the wider local community.
Examples include community land trusts, co-operatives and community benefit societies.
For landowners, working with a community land trust can be an alternative to working with a registered provider.
What Landowners Should Know
Land value. Exception site land is normally valued well below open-market housing land, because the homes must remain affordable.
Affordable housing thresholds do not apply. The usual national restrictions on seeking affordable housing contributions from smaller developments do not apply to rural exception sites.
Partnership matters. Successful schemes are sometimes brought forward with the parish council, the council's housing team and a registered provider or community land trust involved from the start.
Green Belt. Different policies apply in the Green Belt. Policy S5 does not apply there, but Policy GB7(1)(d) does, allowing limited affordable housing for local community needs. See my guide to what is not inappropriate in the Green Belt.
Rural Exception Housing in Practice
In Tendring, I secured planning permission for a rural exception housing scheme of nine dwellings. For wider context, see my guide to the role of the planning system in creating affordable homes.
Related Guides
The presumption in favour of sustainable development: policies S3 to S6
Can you get planning permission outside a settlement boundary?
Planning Advice on Rural Exception Sites
I advise landowners, parish councils and housing providers on rural exception sites. My work covers assessing whether a site is suitable, the evidence of need requirements, the scheme mix and the section 106 arrangements, through to planning applications and appeals. Get in touch for an initial conversation.
Andrew Ransome MRTPI - Email: andrew@andrewransome.co.uk
About me
Andrew Ransome is a Planning Director and a Chartered Member of the Royal Town Planning Institute (RTPI), with more than two decades of experience in town planning.
He specialises in delivering strategic planning solutions for complex developments across both rural and urban environments, helping clients navigate planning challenges and unlock development opportunities. Connect with Andrew on Linkedin.


Planning Policy Information
Recent Planning Approvals


Get in Touch
Email: andrew@andrewransome.co.uk
Tel: 020 7096 8045
London Office:
60 Tottenham Court Road
Fitzrovia
London
W1T 2EW
© 2026 Andrew Ransome Town Planning Ltd. All rights reserved.
Content on this website is provided for general information and educational purposes only and does not constitute formal planning, professional, or legal advice. Planning policies, legislation, and guidance are subject to change. Site-specific assessment by a qualified consultant is recommended before making development decisions.
Projects highlighted across this website represent professional work undertaken by Andrew Ransome throughout his career.