The Guide to the New Local Plan System
How England's new 30-month local plan system works, when councils must start, and when landowners and developers need to get involved to promote land.
PLANNING POLICY
Andrew Ransome
11/6/20268 min read


The way councils in England prepare local plans changed on 25 March 2026. A new plan-making system is now in force.
It requires local planning authorities to prepare a new-style local plan through a structured process designed to achieve adoption within approximately 30 months.
For landowners, site promoters and developers, this matters.
The local plan decides where new homes and employment land will go for the next 15 years or more.
Under the new system there are fewer chances to influence it. The council's overall direction is also set earlier than under the old system. If you wait until a draft plan is published before promoting your land, you may already have left it too late.
This guide explains how the new system works and the key dates councils are working to. It also covers when and how you should get involved.
How Has the Local Plan Process Changed?
Under the old ("legacy") system, councils prepared plans under the 2012 Local Planning Regulations. The familiar stages were Regulation 18 and Regulation 19 consultations, often repeated, with open-ended timetables. Many plans took the best part of a decade. Some never reached adoption.
The new system works under the Planning and Compulsory Purchase Act 2004, as amended by the Levelling-up and Regeneration Act 2023, together with the Town and Country Planning (Local Planning) (England) Regulations 2026. The headline changes are:
A single local plan: one plan per council, rather than a suite of separate documents
A 30-month timetable: from formally starting the plan to adopting it
Three gateways: checkpoints at which the council or the Planning Inspectorate confirms the plan is on track
Three mandatory consultations: with the Government discouraging any additional rounds
Digital-first plans: published plan data, data standards and digital services such as online call-for-sites forms
Rolling plan-making: councils must start a new plan at least every five years after adopting the last one
The 30-Month Process at a Glance
Getting ready (before month 1, with at least 4 months' notice)
What happens: The council publishes a timetable, gives notice it is starting, and runs a scoping consultation lasting at least 21 days, the first of the three mandatory consultations. Most councils will also run a call for sites at this stage
What it means for landowners: Submit your site and respond to the scoping consultation. Early-stage consultations have no prescribed advertising requirements, so check the council's website regularly
Gateway 1 (end of the getting-ready stage)
What happens: The council publishes a self-assessment confirming it is ready. The 30-month clock starts
What it means for landowners: Check the timetable and the evidence the council plans to gather
Consultation on plan content and evidence (months 1 to 23; at least 6 weeks)
What happens: The council consults on its draft vision, objectives and proposed spatial strategy
What it means for landowners: The most important stage for promoting land
Gateway 2 (normally 4 to 6 weeks)
What happens: A Planning Inspector, acting as gateway assessor, holds a workshop with the council (usually no more than two days) and reports on progress and any soundness issues. The council must have regard to the report
What it means for landowners: The report is published on the council's website before the consultation on the proposed plan, and shows the issues the plan still needs to resolve
Consultation on the proposed local plan (at least 8 weeks)
What happens: The full draft plan, a map of proposed policies and allocations, and the evidence are published
What it means for landowners: Make formal representations. This secures the right to be heard at examination
Gateway 3 (4 weeks, or up to 6 by exception)
What happens: An assessor decides whether the plan is ready for examination
Examination (months 24 to 29; around 6 months)
What happens: An independent inspector tests whether the plan is sound
What it means for landowners: Appear at the hearings to argue for your site
Adoption (months 30 to 31)
What happens: Full council adopts the plan. A policies map follows within a month
What it means for landowners: The allocation becomes part of the development plan
Monitoring (month 31 onwards)
What happens: Annual monitoring, a plan evaluation report in year 4, and a new plan started within 5 years
What it means for landowners: The next opportunity to promote land
The Government's own 30-month local plan process overview sets out each stage in more detail.
Why the Spatial Strategy Consultation Matters Most
Many landowners are used to the old pattern. A council would publish an "Issues and Options" document, then "Preferred Options", then a draft plan. Sites could be pressed at each stage.
The new system compresses this.
The first substantive consultation in the 30-month period covers the council's draft vision and proposed spatial strategy: the broad decisions about how much growth goes where.
These include whether growth is concentrated in towns, spread across villages, or delivered through a new settlement or urban extension.
Once that strategy is set, sites that do not fit it are much harder to get into the plan.
Government guidance is clear that councils should run only the mandatory consultations.
It warns that extra rounds will add significant delays. It gives significant changes such as adding or removing sites as an example of a strong reason that might justify another round.
The practical message is that the process is not designed to keep reopening site selection.
If your land depends on a particular spatial strategy, you need to make that case early.
For example, it may depend on growth being directed to a village, or on a settlement boundary being extended. The case should be backed by evidence on accessibility, services and deliverability, and made at the spatial strategy stage, not left to the final draft plan.
Key Dates: When Will Your Council Start?
The new system runs in parallel with the old one for a transitional period.
The dates set out in the Government's rollout guidance are the latest a council can legally start. Councils are free to start earlier.
Councils finishing a plan under the old system
Councils with advanced plans can still submit them for examination under the legacy system. The deadline was originally 31 December 2026.
On 23 October 2026 the Housing and Planning Minister wrote to council leaders extending it to 31 March 2027 for plans that have concluded their final Regulation 19 consultation by 31 December 2026.
The extension does not automatically apply where the Minister has already issued a specific direction for a plan. The Minister described this as "the last opportunity" to submit under the legacy system, adding that there should be no expectation of further extensions. See the Minister's letter.
Once a legacy plan is adopted, the council must:
give notice that it is starting its next plan within 4 years and 8 months of adoption; and
publish its Gateway 1 self-assessment by the time the plan is 5 years old.
All other councils
Councils not submitting a legacy plan must give notice that they are starting a new plan by 31 December 2026, and publish their Gateway 1 self-assessment by 30 April 2027.
If their existing plan is younger, they can instead wait until it is 4 years 8 months old and 5 years old respectively, whichever is later.
Councils that had to start early
Thirty-nine councils were required to give notice by 30 June 2026 and pass Gateway 1 by 31 October 2026. These are councils whose plans were submitted for examination by 12 March 2025, under the transitional arrangements of the December 2024 NPPF, with a draft housing requirement below 80% of local housing need.
Their 30-month clocks are now running.
They include Tunbridge Wells, Horsham, Epsom and Ewell, Spelthorne, St Albans, Dacorum, Chichester and Surrey Heath.
What this means in practice
Across Essex, Kent, London and the wider South East, most councils will be in the getting-ready stage or the early months of a new plan between now and mid-2027.
That means a wave of scoping consultations and calls for sites.
Every council must publish a local plan timetable and keep it up to date. That timetable is the first document to check if you own land with development potential.
Some areas are also going through local government reorganisation.
The Government intends to publish transitional regulations explaining how plan-making will move to new unitary councils.
Its draft guidance says the intention is that existing adopted plans remain in force for the areas they cover until a new unitary-wide plan replaces them. See the Government's guidance on plan-making and local government reorganisation.
What Happens to Planning Applications in the Meantime?
Existing local plans remain part of the development plan until they are replaced. Planning applications must still be decided in accordance with the development plan unless material considerations indicate otherwise.
The August 2026 National Planning Policy Framework (NPPF) gives very limited weight to local policies that are materially inconsistent with national policy.
It also contains a permanent presumption in favour of suitably located development, with specific routes for housing on the edge of settlements.
Where an evidenced unmet need exists, a site does not always need to wait for a local plan allocation.
The Government's guidance also says councils should consider starting a new plan earlier than the five-year deadline where planning decisions are being assessed against the presumption in favour of sustainable development, or where monitoring suggests a five-year housing land supply cannot be maintained until the next plan is adopted.
So there are often two routes to consider in parallel: promoting a site through the plan, and pursuing a planning application under national policy.
My guides on getting planning permission outside a settlement boundary, grey belt land and permission in principle explain the application routes.
My guide to how planning policy is used in decision-making explains how decision-makers weigh local and national policy.
A Checklist for Landowners and Developers
Find your council's local plan timetable. It will show when the notice to commence, the scoping consultation and the call for sites are expected.
Register for consultation alerts. Most councils keep a consultation database. Being on it means you are told when each stage opens.
Submit your site early. Do it at the call for sites, ideally during the getting-ready stage. My guide to the call for sites explains what councils ask for.
Commission proportionate technical work. Access, flood risk, ecology, heritage and landscape issues are best identified and addressed before the council assesses your site, not after.
Evidence deliverability. Councils need confidence that a site is available and achievable. Ownership, promotion or option agreements, developer interest and a realistic timetable all help.
Engage with the spatial strategy consultation. Make the case for the pattern of growth that supports your site.
Make representations on the proposed plan. This is your formal opportunity to support an allocation or object to the plan's omission of your site. It also gives you the right to appear at the examination hearings.
Keep an application route under review. National policy may offer a quicker route to permission than waiting 30 months or more for a new plan.
Planning Policy Representations
The new system rewards early, well-evidenced engagement. I prepare call-for-sites submissions, consultation representations and examination statements for landowners and developers.
I also advise on whether an application under national policy offers a better route in the meantime.
If your council is starting a new local plan and you own land with potential, get in touch for an initial conversation.
Andrew Ransome MRTPI - Email: andrew@andrewransome.co.uk
About me
Andrew Ransome is a Planning Director and a Chartered Member of the Royal Town Planning Institute (RTPI), with more than two decades of experience in town planning.
He specialises in delivering strategic planning solutions for complex developments across both rural and urban environments, helping clients navigate planning challenges and unlock development opportunities. Connect with Andrew on Linkedin.


Planning Policy Information
Recent Planning Approvals


Get in Touch
Email: andrew@andrewransome.co.uk
Tel: 020 7096 8045
London Office:
60 Tottenham Court Road
Fitzrovia
London
W1T 2EW
© 2026 Andrew Ransome Town Planning Ltd. All rights reserved.
Content on this website is provided for general information and educational purposes only and does not constitute formal planning, professional, or legal advice. Planning policies, legislation, and guidance are subject to change. Site-specific assessment by a qualified consultant is recommended before making development decisions.
Projects highlighted across this website represent professional work undertaken by Andrew Ransome throughout his career.