Every council in England has a minimum housing need figure, calculated using a Government formula called the standard method.

That number drives a great deal of planning. It shapes how much land a new local plan must allocate. It often sets the bar against which a council's five-year housing land supply is measured. And it determines whether a council is under pressure to release more land, including in the Green Belt.

For landowners and developers, understanding housing need explains why so many councils are now looking for new sites, and why some are struggling to show a five-year supply.

Housing Need, Housing Requirement and Land Supply: The Difference

Three terms are often confused:

  • Local housing need is the minimum number of homes needed each year, calculated using the standard method in Annex D of the National Planning Policy Framework (NPPF).

  • The housing requirement is the number of homes a local plan commits to providing.

    Policy HO2 of the NPPF says requirements should reflect the extent to which identified needs can be accommodated, as a minimum. They can be higher than local housing need, for example to help meet neighbouring areas' needs or support economic growth.

  • The five-year housing land supply is the stock of deliverable sites the council can identify, compared with the requirement, or with local housing need where the plan's requirement is more than five years old.

How the Standard Method Works

The current method was introduced in December 2024 and is set out in Annex D of the NPPF. It has two steps.

Step 1: the baseline. The starting point is 0.8% of the existing housing stock in the area, using the Government's annual dwelling stock estimates.

Step 2: the affordability adjustment. The baseline is increased where housing is less affordable. The method uses the ratio of median house prices to median workplace-based earnings, averaged over the latest five years:

  • where the ratio is 5 or below, no adjustment is made

  • for each 1% the ratio is above 5, the baseline increases by 0.95%

  • an area with a ratio of 10 therefore sees a 95% increase

There is no cap. The result is a minimum annual figure.

The figures change when new data is published: dwelling stock estimates each spring, and affordability ratios each March.

Housing Need

The list below compares each council's current local housing need with the average number of homes delivered each year between 2022 and 2025.

Focus on Essex

  • Basildon: need of 1,289 homes a year; average of 258 delivered a year (20% of need)

  • Braintree: need of 1,132 homes a year; average of 1,056 delivered a year (93% of need)

  • Brentwood: need of 715 homes a year; average of 369 delivered a year (52% of need)

  • Castle Point: need of 671 homes a year; average of 40 delivered a year (6% of need)

  • Chelmsford: need of 1,448 homes a year; average of 883 delivered a year (61% of need)

  • Colchester: need of 1,275 homes a year; average of 821 delivered a year (64% of need)

  • Epping Forest: need of 1,244 homes a year; average of 333 delivered a year (27% of need)

  • Harlow: need of 639 homes a year; average of 371 delivered a year (58% of need)

  • Maldon: need of 586 homes a year; average of 415 delivered a year (71% of need)

  • Rochford: need of 700 homes a year; average of 397 delivered a year (57% of need)

  • Southend-on-Sea: need of 1,409 homes a year; average of 233 delivered a year (17% of need)

  • Tendring: need of 1,069 homes a year; average of 836 delivered a year (78% of need)

  • Thurrock: need of 1,079 homes a year; average of 338 delivered a year (31% of need)

  • Uttlesford: need of 818 homes a year; average of 739 delivered a year (90% of need)

Focus on Kent

  • Ashford: need of 986 homes a year; average of 692 delivered a year (70% of need)

  • Canterbury: need of 1,199 homes a year; average of 846 delivered a year (71% of need)

  • Dartford: need of 756 homes a year; average of 731 delivered a year (97% of need)

  • Dover: need of 772 homes a year; average of 631 delivered a year (82% of need)

  • Maidstone: need of 1,373 homes a year; average of 928 delivered a year (68% of need)

  • Medway: need of 1,666 homes a year; average of 971 delivered a year (58% of need)

  • Sevenoaks: need of 1,166 homes a year; average of 174 delivered a year (15% of need)

  • Swale: need of 1,070 homes a year; average of 728 delivered a year (68% of need)

  • Thanet: need of 1,106 homes a year; average of 770 delivered a year (70% of need)

  • Tunbridge Wells: need of 1,100 homes a year; average of 621 delivered a year (56% of need)

These figures are not the same as Housing Delivery Test results. For those, see my Housing Delivery Test guide.

The gap is striking in several areas.

Castle Point has averaged around 40 homes a year against a need of 671. Sevenoaks has averaged 174 against 1,166, and Southend-on-Sea 233 against 1,409.

Why Housing Need Matters for Your Site

New local plans must plan for it

Policy S1 of the NPPF requires plans to meet their area's housing needs as a minimum.

The only exceptions are where national policies protecting areas or assets of particular importance give a strong reason to restrict development, or where the adverse impacts would substantially outweigh the benefits.

These protective policies cover:

  • Green Belt

  • National Landscapes

  • habitats sites

  • flood risk

  • designated heritage assets

Plans must also take account of needs that neighbouring areas cannot meet.

With need figures well above previous requirements, most councils will need significantly more land in their next plans. That is why the call for sites process under the new 30-month plan system is so important for landowners.

Older plans are measured against need

Once a local plan's housing requirement is more than five years old, Annex D measures the council's five-year supply against local housing need.

Where need is much higher than the old requirement, a council that previously had a five-year supply can lose it overnight.

Chelmsford, Colchester, Maldon and Ashford all now report shortfalls on this basis.

Recent plans with low requirements face a 20% buffer

Annex D applies a 20% buffer for decision-making where a requirement adopted in the last five years was examined under a pre-December 2024 version of the NPPF, and is 80% or less of current local housing need.

Where this applies, a supply that looks healthy can turn into a shortfall.

The Green Belt

Where a council cannot meet its needs without releasing Green Belt land, its plan must consider changing Green Belt boundaries. Grey belt land and previously developed land come first.

See my guides to how Green Belt boundaries are changed and grey belt land.

Needs of particular groups

Policy HO1 also requires plans to assess the housing needs of different groups.

These include affordable housing, older people, disabled people, renters, families, students, travellers and self-builders. Evidence of unmet need for any of these groups can support a planning application, even where a council has a five-year supply.

Related Guides

Planning Advice on Housing Need

I advise landowners and developers on how housing need affects their sites. That includes promoting land through new local plans, and planning applications and planning appeals where councils are short of housing land. Get in touch for an initial conversation.

Andrew Ransome MRTPI - Email: andrew@andrewransome.co.uk

About me

Andrew Ransome is a Planning Director and a Chartered Member of the Royal Town Planning Institute (RTPI), with more than two decades of experience in town planning.

He specialises in delivering strategic planning solutions for complex developments across both rural and urban environments, helping clients navigate planning challenges and unlock development opportunities. Connect with Andrew on Linkedin.

Planning Policy Information

Recent Planning Approvals

Andrew Ransome RTPI
Andrew Ransome RTPI

Get in Touch

Email: andrew@andrewransome.co.uk

Tel: 020 7096 8045

London Office:

60 Tottenham Court Road

Fitzrovia

London

W1T 2EW

© 2026 Andrew Ransome Town Planning Ltd. All rights reserved.

Content on this website is provided for general information and educational purposes only and does not constitute formal planning, professional, or legal advice. Planning policies, legislation, and guidance are subject to change. Site-specific assessment by a qualified consultant is recommended before making development decisions.

Projects highlighted across this website represent professional work undertaken by Andrew Ransome throughout his career.

Andrew Ransome Town Planning Ltd - Registered in England and Wales. Company Registration No. 17489935. Registered Office: Office 2059, 60 Tottenham Court Road, Fitzrovia, London, W1T 2EW